Performance Metrics

The Performance Metrics panel displays key scheduling and resource metrics for the selected T-Week. Select the Metrics button to show or hide the metrics panel.

MetricFormulaSignificance
Gross Available Hrs (Gross Available Man Hours (GAMH))# Personnel × 40 (or set by shift patterns)The max hours available for the crew.
Borrowed Hrs (BH)Number of scheduled hours borrowed from another crew.

Automatically tracked and added to GAMH for the borrowing crew and subtracted from GAMH for the lending crew.
Lent Hrs (LH)Number of scheduled hours lent to another crew.

Automatically tracked and subtracted from GAMH for the lending crew and added to GAMH for the borrowing crew.
Total Unavailable Hrs (UH)Planned Unavailable Hours + Indirect Maintenance (IM) Scheduled HoursHow much time is taken away from maintenance work.
Net Available Hrs/ Net Available Man Hours (NAMH)Gross available man hours + borrow hours – unavailable hours – lent hoursHow much time is left for the organization to perform maintenance.
% Scheduled(Total Scheduled Hours – Indirect Maintenance (IM) Scheduled Hours )/ NAMHPercent of scheduled NAMH
Sponsored WOs (Work Orders)Total number of sponsored work orders.
Emergency WOs  (Work Orders)Total number of emergency work orders.
Sponsored HrsTotal actual hours worked on sponsored work orders.
Emergency HrsTotal actual hours worked on emergency work orders.
PM (Preventative Maintenance) Compliance# Completed (PROG C or OS) PM WOs / # Scheduled PM WOsHow many preventative maintenance work orders were completed (PROG C or On Schedule) versus scheduled.
Resource UtilizationTotal Actual Hours (Planned + Emergent – IM WOs) / (GAMH + Unplanned Overtime + BH – LH)
Percent of time spent on maintenance work.
Net Hrs AccountedTotal Actual Hours (Planned + Emergent + IM Metric Group + Planned 
& Unplanned Unavailable) / (GAMH + Unplanned Overtime Hours + BH – LH)
Percent actual hours vs NAMH.
Emergent HrsTotal Actual Hours on Emergent WOs / Total Actual HoursPercent actual hours spent on emergent or break-in work.
Actual Unplanned HrsTotal Actual Hours for Emergent Work + Unplanned Unavailable HoursActual hours charged to unplanned work and unavailable time.
Backlog HrsTotal estimated hours for all open work orders.
# of Backlog WO’sCount of all open work orders.
Backlog WeeksBacklog hours/ GAMHHow many weeks of work are in the backlog.
CM (Corrective Maintenance) HrsTotal Actual Hours CM / (Total Actual Hours – Total Actual Hours IM)Percent of actual time spent on Corrective Maintenance activities.
PM (Preventative Maintenance) HrsTotal Actual Hours PM / (Total Actual Hrs – Total Actual Hours IM)Percent of actual time spent on Preventative Maintenance activities.
CD (Condition Driven) HrsTotal Actual Hours CD / (Total Actual Hours – Total Actual Hours IM)Percent of actual time spent on Condition Driven activities.
IM (Indirect Maintenance) Actual Hrs Total Actual Hours IM / Total Actual HoursPercent of actual hours not doing maintenance.
IM Sch (Indirect Maintenance Scheduled) Hrs(Total IM Sched Hours + Total Planned Unavailable Hours) / (GAMH + BH – LH)Percent of total hours scheduled for Indirect Maintenance activities.
WO Completed w/o Hrs (Work Orders completed without hours)How many jobs were completed without actual hours.
Sch Compliance WO#  (Schedule compliance work order number)Work Orders Completed / Work Orders ScheduledPercent of completed jobs vs scheduled jobs.
Sch Compliance Hrs Completed Actual Hours / Scheduled HoursPercent of completed actual hours vs scheduled hours.
Sch Effectiveness1 – [Absolute value of (Scheduled – Actual Hours) / Scheduled Hours] for Completed = Prog = ‘C’ or ‘OS’, Excludes IM Metrics GroupsPercent how well we estimated scheduled hours to complete a job.
Planning Effectiveness1 – [Absolute value of (Planned Weekly (PW) Hrs – Actual Hours) / PW Hours] for Completed = Prog = ‘C’ or ‘OS’, Excludes IM Metrics GroupsPercent how well we estimated Planned Weekly hours to complete a job.
Planned Unavailable HrsTotal planned unavailable hours.
Unplanned Unavailable HrsTotal unplanned unavailable hours.