How to Copy a Work Order

The Copy To function allows a work order to be duplicated into another T-week, making it a multi-week job.

  1. Right-click the work order to be copied and select Copy To from the menu.
  2. In the Work Week Criteria window, validate the crew, select the applicable T-week using the work week calendar or green T-week arrows, and click OK.
  3. Observe that the work order now appears in the additional T-week.