How to Schedule Work Orders to a T-Week

Schedule work orders to a T-Week using one of two methods: drag and drop or right-click scheduling.

Method One: Drag and Drop

  1. Verify that the selected T-week crew matches the work order to be scheduled.
  2. Drag the desired work order into the applicable T-week.
    • Note: If the job is dragged into T-1 after the schedule lock, it becomes emergent.
  3. PaSTA indicates the job is scheduled by displaying a small green indicator on the right side of the Order # cell.

Method Two: Right Click

  1. Right-click the work order and select Schedule Task.
  2. In the Work Week Criteria window, validate the crew, select the applicable T-week using the work week calendar or T-week arrows, and click OK.
    • Note: If the job is placed into T-1 after the schedule lock, it becomes emergent.
  3. PaSTA indicates the job is scheduled by displaying a small green indicator on the right side of the Order # cell.
Was this article helpful?