Overview
Two new project scheduling controls have been added. Users can now lock relationship slack between related work orders and lock milestones to prevent them from being moved unintentionally.
Enhancements
- Right-click lock relationship slack:
- When two work orders have a defined relationship, users can right-click the relationship and select Lock Relationship Slack.
- Once enabled, moving one of the related work orders will move the other with it to maintain their slack.
- When the relationship slack is locked, the connector line between the work orders turns black:

- Right-click lock milestone from moving:
- Milestones can now be locked to prevent them from being moved on the schedule.
- Right-click a milestone and select Lock to enable this setting.
- When locked, the milestone turns black and cannot be moved: